Most First Nations capital projects in British Columbia are funded in stages, and each stage is approved before the next one starts. This page sets out how that usually works with Indigenous Services Canada (ISC) and the First Nations Health Authority (FNHA), what a feasibility study needs to contain, and how we plan community engagement around it.
Funding
The funding stages.
ISC describes five stages for an infrastructure project on reserve. In its BC Region, each funded stage starts with its own application.
01
Identification
The Nation identifies the need, usually through its capital or infrastructure plan, and raises it with its ISC regional office, or with FNHA for a health facility.
02
Feasibility
The Nation chooses a consultant and applies for feasibility funding; in ISC’s BC Region this is a Feasibility Application Request (FAR). The study compares options, recommends one, and includes a Class D construction cost estimate. ISC reviews the draft before it is finalised.
03
Design
With the study accepted, the Nation applies for design funding, a Design Application Request (DAR). The architect and engineers produce the design and the construction documents, and the cost estimate becomes more precise at each step.
04
Construction
The Nation applies for construction funding, a Project Application Request (PAR), tenders the work and awards the contract. The architect administers the contract through construction.
05
Completion
The professional consultant certifies that the project is complete, and the building moves into operation and maintenance.
Health facilities follow FNHA’s process.
Since 2013, FNHA has been responsible for planning, managing, delivering and funding health programs and services for First Nations in BC. Its Health Infrastructure program funds health centres, nursing stations, professional residences, First Nations-led primary care centres and mental health and wellness facilities. A health project still moves from need and feasibility through design to construction, but the submissions and approvals are FNHA’s rather than ISC’s.
Program names, forms and thresholds change, and ISC’s differ between regions. We confirm the current requirements with your ISC or FNHA capital staff at the start of each project.
By building type
Who usually funds what.
| Building | Usual funders |
|---|---|
| Health centres | First Nations Health Authority (FNHA), sometimes with ISC or other sources for non-health space. |
| Fire halls | Indigenous Services Canada, through the fire protection component of its Capital Facilities and Maintenance Program. |
| Community and cultural centres | Indigenous Services Canada for community infrastructure, often with provincial grants or the Nation’s own funds. |
| Housing | ISC’s On-Reserve Housing Program, CMHC’s On-Reserve Non-Profit Housing Program (Section 95), and BC Housing’s Indigenous Housing Fund. |
Feasibility
What a feasibility study contains.
A feasibility study is what the funder decides on, so it has to answer the funder’s questions as well as the community’s. A complete study sets out:
- The need: who the building serves, what it replaces, and why now.
- A space programme: the rooms and areas the services require.
- Site options and analysis: land status, servicing, access, ground conditions and environmental constraints.
- The options compared, and a recommended option.
- A Class D cost estimate and a schedule.
- Operating and maintenance costs, since the Nation carries them after opening.
We prepare feasibility studies and the design and construction submissions that follow them for ISC-funded projects, and coordinate the engineering and cost consultants each study needs.
Engagement
Community engagement.
Engagement is planned with your project lead at the start: who needs to be heard, in what setting, and how decisions go back to Chief and Council. Council meets on its own cycle, so the design schedule is built around it rather than the other way round.
We present in the community as well as to Council, and use drawings, physical models and virtual reality so people can see the building and argue with it before it is committed to.
Nothing about a Nation’s project, whether text, image or name, is published by us without written approval from the community’s designated contact.
Questions
Common questions.
Can Unison prepare our feasibility study for ISC funding?
Yes. We prepare feasibility studies and the design and construction submissions that follow them, and coordinate the engineering and cost consultants the study needs.
Who chooses the architect on an ISC-funded project?
The First Nation does. ISC funds the work, but the Nation selects and contracts its consultants, and ISC reviews the feasibility study before it is finalised.
What is a Class D cost estimate?
An early estimate based on the space programme and a concept, before detailed design. It is the least precise class of estimate; it is refined to Class C, B and A as the design develops.
Do you work with Nations outside British Columbia?
We provide services in Canada, except Quebec, and the USA. Our architectural licence is for British Columbia (BC) only. For projects in other regions, we partner with local architects and builders to deliver the project.
Consultation
Starting a capital project?
Tell us about the community, the site and what the building needs to do. We will come back to you about how a consultation could work.